Navigate to...

Overview
Complete
Joe Construction Inc. / 07 Aug 2019 / Shee Arnai
Dust Risk Assessment Template
Inspection score
80%
Failed items
0
Created actions
1
Site
Joe Construction Inc.
Date and Time of Assessment

7th Aug, 2019

7:00 AM +08

Safety Officer (Full Name)
Shee Arnai
Location
186 Exhibition St, Melbourne VIC 3000, Australia
Actions
1
Inspection
1
80%
Overview
Description of procedure, task or worksite being assessed
Water pipeline construction
Risk Matrix and Hierarchy of Controls
Risk Matrix Reference:
Hierarchy of Controls Reference:
Hazard
80%
Hazard / Hazard 1
100%
Description of hazard
Road drill - inhalation of construction dust
Photo of hazard (optional)
Photos
Type of Dust
Respirable dust
Notes
The magnitude of potential dust emissions from construction works would be medium
Hazard / Hazard 1 / Risk Rating
100%
Consequences
Major Injuries
Likelihood
Unlikely
Risk Rating (refer risk matrix above)
Medium
Hazard / Hazard 1 / Controls
1
Select control measures
Engineering Controls
PPE
Actions
To do
Provide respirator mask
Description of support measures
- Put barricade to isolate drill operation from pedestrians - Wear appropriate PPE (respirator mask)
Hazard / Hazard 2
60%
Description of hazard
Truck out - inhalation of construction dust
Photo of hazard (optional)
Unanswered
Type of Dust
Inhalable dust
Notes
The magnitude of potential dust emissions from track out could be medium at receptor locations in close proximity to the temporary haul roads.
Hazard / Hazard 2 / Risk Rating
100%
Consequences
Minor Injuries
Likelihood
Likely
Risk Rating (refer risk matrix above)
Medium
Hazard / Hazard 2 / Controls
Select control measures
Administrative Controls
Description of support measures
- Ensure driver receives proper training on load handling
Completion
Recommendations
Administer recommended controls identified in this report
Name and Signature of Safety Officer
Shee Arnai
7th Aug, 2019 11:38 AM +08
Media summary