JK 2019-332896 / Kitchen Remodeling for Mrs. Martinson / Mrs. Thelma Martinson:
Scope of Work TemplateConducted on22 Feb 2019BySafetyCulture Staff
Failed items
0
Created actions
0
Project Title
Kitchen Remodeling for Mrs. Martinson
Project No.
JK 2019-332896
Contractor
JK Construction Services
Client
Mrs. Thelma Martinson:
Scope of Work
Overview
Project Statement
Mrs. Thelma Martinson has a requirement to remodel her home kitchen at 1974 Barrington Court, Dermott, Arizona. Ms. Martinson has contracted JK Construction to design and execute the job. This home kitchen remodelling will begin with a planning and design phase that will ensure all requirements and preferences for the customers, demolition, and construction are met, while being cost-efficient. All materials used for installation of mechanical, electrical, paint, cabinetry, or appliances shall meet safety and efficiency standards imposed by the International Housing Code.
Project Schedule
Summary of Schedule
Submission of Execution Plan: March 5, 2019 Owner Review of Execution Plan:March 6-7, 2019 Approval of the Execution Plan:March 8, 2019 Demolition:March 11, 2019 Start of Construction/ Installation:March 11, 2019 Substantial Completion of the Work: March 22, 2019 Testing of Equipment for Proper Function:March 27, 2019 Clean up:March 28, 2019 Handover of Work:March 29, 2019
Attach supporting documents (Optional)
Photos
Scope of Work
Scope of Work Statement
To remodel the kitchen within the existing structure of the residential unit in a period of four weeks, to be delivered by March 29, at a cost of no greater than $14,000. This includes the design, preparation and installation to US Standards and ergonomically designed for the clients use. •Kitchen remodel project plan, color scheme, design layout, and strata sign off • Kitchen that includes the following: o Curved center island with space for 4 bar stools o White tile countertops o High-end vitroceramic cooktop with island mount chimney hood o Upper and lower slab cabinets (cranberry red color) with crown molding
Definition of Terms
In this Scope of Work Document, the following words or phrases are deemed to be interchangeable between this Scope of Work and stated definitions contained in other Project contract documents. “Contract” to refer broadly to all of the contract documents between the Owner and Contractor established and stated in those contract documents. “ Specifications” are those documents consisting of the written requirements of the Work referred to in the list of Contract Documents. “Standard of Performance” means performance of the Work within the standards and practices that would be exercised by a competent and experienced contractor, performing similar work with similar experience in a similar market and similar site conditions, and in accordance with the specific requirements that are set out in the Contract (the “Standard of Performance”). “Fixtures & Fittings” means the taps required for the sink unit, handles for all doors and drawers, new covers for electrical points and light. “Electrical Appliances” means, microwave, cook top, range hood, oven, dishwasher, front loading washing machine and fridge. “Work” refers to the services, products, materials and other responsibilities set out in this and other Contract documents.
Attach supporting document/s (Optional)
Photos
Scope of Work / List the deliverables needed to accomplish the goal
Scope of Work / List the deliverables needed to accomplish the goal / Deliverable 1
Description
Completion of planning and kitchen design execution plan
Costs
$1,500
Responsible Person
Ar. Andy Beckinson
Target Date

6th Mar, 2019

Attach supporting documents (Optional)
Unanswered
Scope of Work / List the deliverables needed to accomplish the goal / Deliverable 2
Description
Demolition of old cabinets and countertop
Costs
$700
Responsible Person
Tom Cena
Target Date

15th Mar, 2019

Attach supporting documents (Optional)
Unanswered
Scope of Work / List the deliverables needed to accomplish the goal / Deliverable 3
Description
Completion of construction of countertop and upper and lower slab cabinets
Costs
$10,150
Responsible Person
Tom Cena
Target Date

26th Mar, 2019

Attach supporting documents (Optional)
Unanswered
Scope of Work / List the deliverables needed to accomplish the goal / Deliverable 4
Description
Testing and inspection of all electrical and mechanical equipment
Costs
$650
Responsible Person
Tom Cena
Target Date

27th Mar, 2019

Attach supporting documents (Optional)
Unanswered
Scope of Work / List the deliverables needed to accomplish the goal / Deliverable 5
Description
Total clean-up of appliances, countertops, cabinets, and remaining debris
Costs
$500
Responsible Person
Tom Cena
Target Date

28th Mar, 2019

Attach supporting documents (Optional)
Unanswered
Scope of Work / List the deliverables needed to accomplish the goal / Deliverable 6
Description
Full turnover of remodeled kitchen and handover of full payment by Mrs. Martinson
Costs
$500
Responsible Person
Chris Ford
Target Date

29th Mar, 2019

Attach supporting documents (Optional)
Unanswered
Project Costs
Summary of Costs
Planning and Design - $1,500 2. Demolition - $700 3. Construction - $10,150 4. Testing and Inspection - $650 5. Clean-up - $500 6. Turnover - $500
Project Approval & Signatures
Client
Client Representative's Full Name and signature
Thelma Martinson
22nd Feb, 2019 12:08 PM +08
Complete Address
1974 Barrington Court, Dermott, AR 71638
Contact Details
870-521-9580
Date Signed

8th Mar, 2019

4:30 PM +08

Client / Add signatory
Contractor
Contractor's Representative's Full Name and signature
Chris Ford
22nd Feb, 2019 12:09 PM +08
Job Title
Project Manager
Complete Office Address
3261 Martha Street, Prescott, AR 86301
Contact Details
928-642-9179
Date Signed

5th Mar, 2019

5:00 PM +08

Contractor / Add signatory